QUESTION NO 87
Privatisation in Railways
87 SHRI ANIL KUMAR SAHANI
Will the Minister of RAILWAYS be pleased to satate :-
(a) whether Government plans to privatise Railways; and
(b) the number of projects of Railways in which Government plans for Foreign Direct Investment, the details thereof?
MINISTER OF RAILWAYS (SHRI SURESH PRABHAKAR PRABHU)
(a): No, Sir.
(b): Ministry of Railways have based on initial assessment identified the following potential projects for Domestic/Foreign Direct Investment:
1. Suburban Corridor projects through PPP
| S.No | Project | Kms | Cost (Rs Crore) |
| 1. | CSTM-Panvel | 49 | 14,000 |
2. High speed train projects
| S.No. | Project | Kms | Cost(Rs Cr.) |
| 1. | Mumbai-Ahmedabad | 534 | 63,180 |
| 2. | Chennai-Banglore-Mysore | – | – |
3. Freight lines
| S.No. | Project | Kms | Cost(Rs.Cr.) |
| 1 | Dankuni-Gomoh New line | 282 | 4500 |
| 2 | Whitefield-Kolar (52.9 km) New Line | 52.9 | 353.45 |
| 3 | North- South DFC-New Line | – | – |
| 4 | Ajmer-Bangurgram -Doubling | 48.43 | 144.57 |
| 5 | Durg-Rajnandgaon 3rd line | 31 | 152.99 |
| 6 | Wardha(Sewagram)-Nagpur 3rd line | 76.3 | 297.85 |
| 7 | Kazipet-Vijaywada 3rd line with electrification | 219.6 | 1054.35 |
| 8 | Bhadrak-Nergundi 3rd line | 80 | 837.33 |
| 9 | Sambalpur-Talcher DL | 174.1 | 679.27 |
| 10 | Manoharpur-Bondamanda 3rd line | 30 | 258.2 |
| 11 | Rajkharswan-Chakradharpur 3rd line (20 km) | 20 | 174.49 |
4. Rolling stock including train sets and locomotives or coach manufacturing and maintenance facilities
| S.No | Project | Quantity | Cost (Rs. Cr) |
| 1 | Rail Coach Factory, for manufacture of modern 3 phase MEMU/EMU coaches equipped with IGBT technology at Kachrapara. | Approximate 500 EMU/ MEMU coaches annually | 1,200 |
| 2. | Rail coach factory for manufacturing of Aluminum coaches at Palakkad | Approximately 400 coaches per annum | 550 |
| 3. | Periodic overhauling of wagons at Sonpur | Approximately180 wagons per annum | 300 |
| 4. | Midlife rehabilitation of coaches at Anara | Approximately 250 coaches per annum | 185 |
| 5. | Locomotive maintenance depots at Barauni, Daund, Mughal-sarai, Bonda-munda. | – | 300 |
5. Railway Electrification Projects
| S.No | Project | Kms | Cost ( Rs . Cr) |
| 1 | Katwa-Azimganj-Nalhati & Azimganj-Tildanga/New Farakka | 200 | 229.26 |
6. Signaling System
| S.No | Project | Kms | Cost (Rs. Cr) |
| 1. | Agra-Gwalior, A route: provision of automatic signaling along with train protection system to enhance line capacity. | 118 | 250 Cr. |
| 2. | Gwalior – Burhpura A route: Provision of automatic signaling along with train protection system to enhance line capacity | 126 | 280 Cr. |
| 3. | Burpura-Bina, A Route: Provision of automatic signaling along with train protection system to enhance line capacity. | 126 | 270 Cr. |
7. Passenger Terminals
| S.No | Project |
| 1 | Habibganj |
| 2 | Shivaji Nagar |
| 3 | Anand Vihar |
| 4 | Bijwasan |
| 5 | Chandigarh |
| 6 | Surat |
| 7 | Gandhinagar |
| 8 | Manglore |
| 9 | Ernakulam |
| 10 | Vijayawada |
| 11 | Nagpur |
| 12 | Byappanahalli |
| 13 | New Bhubneshwar |
8. Railway Technical Training Institutes.
| S.No | Project | Quantity | Cost (Rs. Cr) |
| 1. | Advanced Training Institute (ATI) for training of Technical staff and Loco Pilots | 6 Training Centres with Driving Simulators at Mughalsarai (ECR),Kurla (CR),Asansol (ER),Vishakapatnam (ECoR),Kanpur (NCR) and Avadi (SR) | 120 |
9. Mechanized Laundry
| S.No | Project |
Quantity
|
Cost (Rs. Cr) |
| 1. | Mechanized laundries at identified locations of different capacities. | 1T/2T/3T/5T per day | 100 |
Source: RajyaSabha.nic.in
Stay connected with us via Facebook, Google+ or Email Subscription.
Subscribe to Central Government Employee News & Tools by Email [Click Here]
Follow us: Twitter [click here] | Facebook [click here] | Google+ [click here]
Admin

COMMENTS